Home / Installation and Commissioning
LuminBlock H · from delivery to first cycle

Installation and Commissioning

The cabinet arrives assembled and pre-wired. What the site provides is the surface it stands on, the cables into it, and the person who signs the commissioning report.

What the site has to be ready with, so the work is planned rather than discovered.

5 t minimum foundation bearing9 commissioning checks2,000 m maximum site altitude20.0 N·m busbar torque
SITE

Four Site Conditions Rule the Plan

Installation needs a concrete or solid-brick pad rated above 5 tonnes and level to 3 mm, with 600 mm above the cabinet and 1000 mm front and back. Torque terminals to 20 N·m and earth at two points. Commissioning covers appearance, earthing, insulation, cable torque, breaker settings, sensor covers and communications.

ConditionLimit
Discharge temperature−20 °C to +55 °C
Charge temperature0 °C to +55 °C
Altitude2,000 m maximum
Fire separationRequired, or a fire wall between the cabinet and the building

Keep the cabinet off flood-prone ground and reserve a water connection for fire service use. If the site sits within a kilometre of the coast, the corrosion class moves to C5 and that has to be in the contract, not added later.

BASE

The Foundation Carries Five Tonnes

Concrete or solid brick, bearing capacity above 5 t, level within 3 mm across the footprint and tilt no more than 5°. The cabinet is fixed with expansion bolts, and the footprint is 1349 by 990 mm.

Clearances are part of the foundation plan: 600 mm above, 1,000 mm at the front and back, a door swing of 105°, and 1,000 mm between parallel units.

CABLES

Sizes and Breakers Follow the Run

CircuitCable and breaker
Protective earth≥16 mm², sized by the run
GRID, BACK-UP, GEN≥21 mm² outdoor copper, breakers ≥250 A and ≥200 A
PV strings≥5 mm², DC breaker ≥32 A per string
Network and dry contactCAT5 or better, shielded 0.2–0.4 mm²

Cables are supplied by the customer. Torque the busbar to 20.0 N·m and check it again after the first week of cycling.

EARTH

Earth Goes On First and Comes Off Last

Connect protective earth before any power conductor, and remove it last when the cabinet is taken out of service. Every parallel unit gets its own earth conductor back to the bar.

Power-up and shut-down sequences run four steps up and six steps down. They are written in the installation manual that ships with the unit, and the commissioning engineer follows that copy rather than a site sketch.

COMMISSIONING

Nine Checks Before the First Cycle

  1. Appearance and shipping damage, including the door seal.
  2. Mechanical fixings and the expansion bolts.
  3. Two-point earth resistance measurement.
  4. Insulation resistance on each circuit.
  5. Cable terminations, sizes and torque.
  6. Hole sealing where cables enter the cabinet.
  7. All breakers open and the SPD indicator window green.
  8. Temperature and smoke sensor covers removed.
  9. Communications up, with the meter and the cloud link visible.

The signed checklist is the handover document. Keep a copy on site, because the first service visit starts from it.

INSTALLATION

What Battery Storage Installation Involves

Battery storage installation has four stages: a site survey, an electrical design for the switchgear and CTs, the physical install of the pad and cabinet, and commissioning with a signed report. The cabinet arrives pre-assembled and pre-tested, so most site work is hoisting, cabling and verification rather than assembly.

StageWhat happensWho signs it off
SurveyPad condition, cable route, switchgear ratings, CT positionSite engineer
DesignBreaker sizes, cable sizes, earthing, grid applicationElectrical designer
InstallHoisting, fixing, AC and DC terminations, torque checkCertified crew
CommissioningInsulation, breaker settings, sensors, communications, test reportCommissioning engineer

Solar battery storage installation adds one check: the array's DC design has to sit inside the cabinet's MPPT window before the PV cable is pulled. If the array is already running, the check is done from its string data rather than from the roof.

FAQ

Questions about installation and commissioning

Who supplies the cables?

The customer. Outdoor copper is specified by size on this page, and the run length decides the final cross-section.

Can the cabinet be installed indoors?

Yes, with fire separation or a fire wall. The enclosure is IP55, so outdoor installation is also within its rating.

How long does commissioning take?

One working day for a single cabinet when the site is ready. Parallel groups take longer because each unit needs its own address.

What if the site is above 2,000 m?

The cooling margin changes and the rating has to be checked case by case before the order is placed.

Which way should the CT face?

The CT sits on the grid-side conductor with its P1 side toward the utility. Reversed, the cabinet reads import and export the wrong way round, so export limiting and peak control act on a false number. The commissioning checklist includes a direction check before any meter reading is recorded.

Who supplies the meter and the CT?

They are selected per project rather than fixed inside the cabinet: a DTSU208 meter and a CT sized to the incoming current, from 400 A:5 A for a single unit up to 800–2,500 A:5 A as the parallel group grows. Agree at survey who supplies and mounts them; if the utility or the switchgear supplier provides them, send the ratio so the settings match.

How are firmware updates delivered?

Over the air through the cloud link, and most software faults are closed without a site visit. Cabinets ship with matched firmware versions, and commissioning records the version per unit so a mixed-version group is caught before it runs.

Is there an emergency stop?

Yes. An emergency power-off (EPO) button is fitted to the cabinet. It stops the system; clear the fault and follow the restart procedure before energising again. The EPO does not replace the AC isolator or the battery breaker.

Do I need a data logger or a smart meter?

The DTSU208 three-phase meter ships with the cabinet. CTs are separate project items, chosen by incoming current (400 to 2,500 A, 5 A secondary). For cloud access, the iEMS gateway or an optional stick logger provides the data link; the iEMS is the usual choice when units run in parallel.

What does a commercial solar battery installation involve?

A foundation, a cable route, breakers, earthing, and nine checks before the first cycle. Hoisting and connection are one day; the PV array, if there is one, is a separate scope. We hand over the commissioning report, the drawings and the insurance pack.

How much clearance does the cabinet need?

A 600 mm gap above the enclosure and 1,000 mm at the front and back, with the door opening to 105 degrees. Parallel cabinets need 1,000 mm between them, and a battery cabinet needs 600 mm above with 1,000 mm front and back.

What breaker sizes does the site provide?

The installation drawing for your model carries the numbers. For a single 60 kW unit the grid breaker is 250 A or larger, the backup and generator breakers 200 A or larger, and each PV string 32 A or larger. Smaller models take proportionally smaller breakers.

What earthing does the cabinet require?

Two separate earth points, with a protective conductor of at least 16 mm² (5 AWG). Earth the cabinet before any other connection and disconnect the earth last.

What if the cabinet stands for months before installation?

Keep it dry, off the ground and out of the weather. If it is stored for more than six months before energising, recharge the packs to at least 50% state of charge first. Do not take delivery into an open yard and leave it there.

What drives solar battery installation cost, and what is not included?

Solar battery installation cost is the site work: foundation, cable run from the cabinet to the switchgear, hoisting, commissioning and the grid application. The cabinet arrives pre-wired, so the electrical work at site is connection and testing rather than assembly.

How long does solar battery installation take?

How long does solar battery installation take depends on the cable run and the switchgear, not on the cabinet. A like-for-like replacement is a day or two on site; a new foundation and a long cable run add most of the extra time.

How long does battery storage installation take?

The site work is usually one to three days once the pad and cable route exist: hoisting and fixing one day, AC and DC connections and commissioning one to two days. The long items are the pad, the cable route and the DNO application, and those start before the cabinet ships.

What do solar battery storage installers cost?

Installers charge for labour and commissioning, and the amount depends on the cable route, the pad and the switchgear work rather than on the cabinet size. Ask for those three as separate lines. A quote that bundles them into one 'installation' figure cannot be compared with another installer's.

The Site Address Comes Before the Order

Ground conditions, sea distance and the cable run decide lines that a datasheet cannot answer.