What Was Built, and Where
625 kW / 1.3 MWh peak shaving — China
Five LuminBlock 125 kW / 261 kWh cabinets on a two-shift moulding and assembly plant. The manufacturer reports about USD 46,500 a year in avoided electricity spend.
250 kW PV + 522 kWh + 240 kW charger — Poland
Two 110 kW inverters, two 125 kW / 261 kWh cabinets and one 240 kW DC charger, dispatched as one plant and able to run off-grid.
208 kW of charging — Romania
Four 22 kW AC stations and one 120 kW DC charger inside a logistics depot's existing power envelope, with load sharing and one access-control platform.
175 kW PV + 300 kWh storage — Spain
Seven 25 kW hybrid inverters and five 60 kWh cabinets for self-consumption, evening cover, backup of essential circuits and peak shaving.
How These Differ From a LuminBlock H Project
The method is the same. The hardware is not, and the difference matters when you read a capacity figure.
- The cabinet. These projects use the LuminBlock 125 kW / 261 kWh cabinet, or 60 kWh battery cabinets with three-phase hybrid inverters. The LuminBlock H cabinet is 37.5–60 kW and 80–120 kWh in one enclosure.
- The architecture. The larger projects separate conversion, storage and, in Poland, charging into different boxes. The H cabinet puts the inverter, the battery, the transfer switch and the diesel interface inside one outdoor cabinet.
- The scale. A 625 kW plant is roughly ten H60X120 cabinets working in parallel. A campus like the Spanish one is closer to three H100 cabinets, distributed across buildings.
- What carries over. The load profile, the tariff logic, the essential-load list and the question of what the site must keep running during an outage.
What Each Project Page Gives You
- The site and the load: what the site does, when demand peaks, and what cannot be switched off.
- The problem in the bill: what the meter records and why it costs money.
- What was built: the device list and the operating mode, as published.
- What the manufacturer reports: the benefits as stated by the manufacturer, attributed to them.
- How an H project would differ: the same question answered for the cabinet this site covers.
Use these pages as a reference for the shape of a project, not as evidence of what an H cabinet has measured. The sizing sheet shows how the arithmetic works for a 37.5–60 kW cabinet; the projects show what a finished deployment looks like at a larger scale.
Questions about these projects
Are these LuminBlock H installations?
No. They were built with the LuminBlock 125 kW / 261 kWh cabinet or with three-phase hybrid inverters and 60 kWh battery cabinets. We list them because they are real deployments by the same manufacturer, and because the sizing method is the same. We do not present them as LuminBlock H references.
Can I see the original project pages?
Yes. Each project page shows what the manufacturer reports for that deployment. The figures are theirs, not measurements we took, and the page says so at every line.
Why include projects built with a different cabinet?
Because most buyers have never seen a C&I storage project finished. Four real sites show the device list, the operating mode and the benefits claimed, which is more useful than another block of marketing copy. What they do not show is how a 37.5–60 kW H cabinet performs, and we say so on every page.
Can you build a page like this for my site?
Yes — start with the form, and our sales team asks for one recent bill, a 15-minute load profile if you have one, the essential-load list and the transformer rating. We size the cabinet from those inputs and write the assumptions down.
Request a Quote for a Site Like This
Seven fields, no attachments. We aim to reply within two working days of a complete enquiry, with the scope broken out and every assumption written down. If a cabinet does not make sense for your site, we say so.