Six Inputs Do Most of the Work
Size from the bill, not the datasheet. Peak kW sets the power rating; daily energy shifted between cheap and expensive hours sets capacity, at 90% usable. PV can be oversized to 200% of the inverter. Then check the site limit: one cabinet, three extra battery cabinets, or a parallel system up to ten units.
| Input | Where to find it | Why it matters |
|---|---|---|
| Daily kWh | A year of bills divided by days, or one recent bill | Sets the energy ceiling |
| Maximum continuous load | Half-hourly meter data | Sets the power rating |
| Inrush load | Motor and pump nameplates | Covered by the 150% overload |
| PV kWp | Array plan or existing inverter | Capped at 200% of rating |
| Backup minutes | Your own outage policy | Turns into usable energy |
| Parallel intent | Growth plan | Decides one unit or several |
Five Steps in Order
- Power from the peak Take the highest half-hourly load. If it is above 60 kW, the unit count starts at two.
- Energy from the window Backup hours times the load you back up, divided by 0.9, gives the nameplate energy.
- Check the PV ratio Array kWp should stay at or below twice the cabinet kW rating.
- Pick the model Smaller of the models that covers both the power and the energy.
- Check the limits 480 kWh per system, ten units in parallel, then temperature and altitude.
Three Worked Examples
| Inputs | Cabinet | Usable | Runtime at peak |
|---|---|---|---|
| 25 kW peak, 2 h window, 30 kWp PV | BES-H37.5X80 | 72 kWh | 2.9 h at 25 kW |
| 45 kW peak, 2 h window, 60 kWp PV | BES-H50X100 | 90 kWh | 2.0 h at 45 kW |
| 80 kW peak, 3 h window, 100 kWp PV | Two BES-H60X120 | 216 kWh | 2.7 h at 80 kW |
The third row shows where parallelism starts. An 80 kW peak cannot sit under a single 60 kW inverter, so the count goes to two before the energy is considered.
What the Numbers Give You
The output is a model, a unit count, and a note on whether battery cabinets are needed. From there the runtime table follows: 2, 4, 6 and 8 hours at the chosen power.
A 60 kW cabinet with one battery cabinet runs 3.6 hours at full power. With three it reaches 480 kWh, which is eight hours. Those are the two steps most sites choose between.
Where the Estimate Stops
Temperature, altitude and corrosion class are not in the six inputs. A site above 2,000 m, a coastal site inside one kilometre, or a plant that runs above 55 °C ambient changes the answer.
The survey covers foundation, clearances and the cable route. Those decide scope lines rather than cabinet count, and they are the ones a buyer most often forgets.
Questions about BESS sizing sheet
Is this a design?
No. It is an estimate for budgeting and for checking a proposal. A design needs the survey, the single-line diagram and the grid application.
Why divide by 0.9?
Usable energy is 90% of nameplate because the cabinet stops at 90% depth of discharge. A 120 kWh cabinet gives 108 kWh.
What if my peak lasts minutes?
Use the half-hourly figure anyway. Short peaks are what the 150% overload for 10 s covers, and the meter settles on the half-hour.
Can I size for PV only?
Yes, but keep the array at or below 200% of the cabinet rating. More panels do not add storage, they add clipping.
How much battery storage do I need?
Start with the load you want to hold and for how long: usable kWh is kW multiplied by hours. Then add the peak you want to shave and check it against 72, 90 or 108 kWh usable and the ten-unit ceiling. The sheet works it through in five steps.
How do I calculate battery storage size?
How to calculate battery storage size: start from the load you must carry and for how long, not from a kWh number you have seen. Peak-kW x hours = kWh for backup; daily shift x usable energy = kWh for arbitrage. This sheet runs both.
How much battery storage for solar panels do I need?
How much battery storage for solar panels depends on the evening load you want to cover, not on the array size. Take the kW you need after sunset and multiply by the hours; that kWh figure, divided by 0.9, is the nominal size to price.
Run Your Figures, Then Have Them Checked
Start with the form. Our sales team asks for the six inputs and the site address. The reply marks where the estimate holds and where the survey would move it.